[General] Preview countdown: milestone review

Katie Capps Parlante capps at osafoundation.org
Fri Aug 3 12:42:43 PDT 2007


I have the current date for updating the Hub at Monday, *August 20*.
I have the current launch date at Monday, *August 27*.

Jared has said we might not need a week gap, so in theory we could 
"launch" a little earlier if we hit Aug 20th.

The Aug 20th date is fairly precarious, as both the desktop and server 
Zero Bug Release milestones are in danger of slipping a bit.

Next big milestones:

Desktop ZBR: Monday, *Aug 6*
Server ZBR: Thursday, *Aug 9*

I've updated the master list with current dates, doc milestones and 
launch plan items:
http://chandlerproject.org/Planning/PreviewReleaseCountdown

I'll follow up with a note about the doc milestones separately.

Thanks for the updates, all.

Cheers,
Katie

Katie Capps Parlante wrote:
> Ok, I finally got a chance to sit down and review the Preview 
> deliverables more carefully. We have many moving parts here, and I want 
> to make sure we have the consolidated list of major milestones. 
> (Apologies for any repetition or if I'm missing details we've already 
> covered several times.)
> 
> I hit the virtual *triage* button on the Preview Countdown page, moving 
> all of the DONE items out of view so that we can focus on what is left.
> 
> I'd like to refactor the remaining items to be tracking the big 
> milestones that we need to watch. I need help getting them right.
> 
> http://chandlerproject.org/Planning/PreviewReleaseCountdown
> 
> Desktop Release Countdown
> -------------------------
> 
> + Code Complete (*done* July 15)
> + Code Dependent Branding/Docs (*done* July 20)
> + qacosmo running 0.7 Server (*done* July 23)
> + Zero Bug Release (eta: August 6)
>    - Create 0.7 branch
>    - Create daily release candidates
> + Release (eta: August 13)
> 
> Questions for desktop team:
> - *Philippe* and *Aparna*, do you agree with these dates?
> - Do we need to note/track any other milestones?
> 
> Server/Hub Release Countdown
> ----------------------------
> 
> + Feature Complete (*done* ~July 5)
> + 0.6.1.1 on Hub (*done* July 11)
> + 0.7 Code Depenedent Branding/Docs (eta: ?)
> + 0.7 Code Complete (eta: ?)
> + 0.7 Release (+1 wk)
> + Hub updated to 0.7 (+1.5 wk)
> + Preview launch (+1 wk)
> 
> One item left for for code dependent branding/docs: final copy review
> 
> Questions for Server/Hub team:
> - *Ted*, what is eta for CC?
> - *Ted*, *Jared*, *Aparna*: do I have the right deltas for setting the 
> remaining milestones? I'm basing this on the deltas in Sheila's list. If 
> we need to renegotiate, lets do that, and do our best to have 
> reality-based estimates.
> - *Jared*: you are tracking a more detailed list. Any high level 
> milestones that are missing?
> 
> Non-Code Deliverables
> ---------------------
> We don't have the same dependency chain of milestones for these (with 
> possibly the exception of the Hub-related items). The big ticket 
> deliverables:
> 
> + Product FAQ
> + Feature List
> + Known Issues
> + Quickstart guide
> + Screencasts
> + Release Notes
> 
> + Hub branding/doc
> + Terms of Service, Privacy Policy
> + NOC Run Book
> 
> + Vision document
> + OSAF FAQ
> + OSAF website (push out)
> + Sundry blog/wiki/website details
> 
> + Announcements, blending into launch plan
> 
> *Jared*: I think I need a more clear picture of Hub branding/doc tasks, 
> beyond updating the FAQ. I know we've talked about them, but a pointer 
> to a clear summary would help me.
> 
> *All*: Any missing big ticket items? Perhaps the thing to do is set 
> dates for completed draft and final copy.
> 
> Launch Plan Countdown: I'll integrate Ted's proposal, and follow up with 
> any questions after I've done that.
> 
> Cheers,
> Katie
> 
> 
> _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
> 