[General] Preview countdown: milestone review
Katie Capps Parlante
capps at osafoundation.org
Fri Aug 3 12:42:43 PDT 2007
I have the current date for updating the Hub at Monday, *August 20*.
I have the current launch date at Monday, *August 27*.
Jared has said we might not need a week gap, so in theory we could
"launch" a little earlier if we hit Aug 20th.
The Aug 20th date is fairly precarious, as both the desktop and server
Zero Bug Release milestones are in danger of slipping a bit.
Next big milestones:
Desktop ZBR: Monday, *Aug 6*
Server ZBR: Thursday, *Aug 9*
I've updated the master list with current dates, doc milestones and
launch plan items:
http://chandlerproject.org/Planning/PreviewReleaseCountdown
I'll follow up with a note about the doc milestones separately.
Thanks for the updates, all.
Cheers,
Katie
Katie Capps Parlante wrote:
> Ok, I finally got a chance to sit down and review the Preview
> deliverables more carefully. We have many moving parts here, and I want
> to make sure we have the consolidated list of major milestones.
> (Apologies for any repetition or if I'm missing details we've already
> covered several times.)
>
> I hit the virtual *triage* button on the Preview Countdown page, moving
> all of the DONE items out of view so that we can focus on what is left.
>
> I'd like to refactor the remaining items to be tracking the big
> milestones that we need to watch. I need help getting them right.
>
> http://chandlerproject.org/Planning/PreviewReleaseCountdown
>
> Desktop Release Countdown
> -------------------------
>
> + Code Complete (*done* July 15)
> + Code Dependent Branding/Docs (*done* July 20)
> + qacosmo running 0.7 Server (*done* July 23)
> + Zero Bug Release (eta: August 6)
> - Create 0.7 branch
> - Create daily release candidates
> + Release (eta: August 13)
>
> Questions for desktop team:
> - *Philippe* and *Aparna*, do you agree with these dates?
> - Do we need to note/track any other milestones?
>
> Server/Hub Release Countdown
> ----------------------------
>
> + Feature Complete (*done* ~July 5)
> + 0.6.1.1 on Hub (*done* July 11)
> + 0.7 Code Depenedent Branding/Docs (eta: ?)
> + 0.7 Code Complete (eta: ?)
> + 0.7 Release (+1 wk)
> + Hub updated to 0.7 (+1.5 wk)
> + Preview launch (+1 wk)
>
> One item left for for code dependent branding/docs: final copy review
>
> Questions for Server/Hub team:
> - *Ted*, what is eta for CC?
> - *Ted*, *Jared*, *Aparna*: do I have the right deltas for setting the
> remaining milestones? I'm basing this on the deltas in Sheila's list. If
> we need to renegotiate, lets do that, and do our best to have
> reality-based estimates.
> - *Jared*: you are tracking a more detailed list. Any high level
> milestones that are missing?
>
> Non-Code Deliverables
> ---------------------
> We don't have the same dependency chain of milestones for these (with
> possibly the exception of the Hub-related items). The big ticket
> deliverables:
>
> + Product FAQ
> + Feature List
> + Known Issues
> + Quickstart guide
> + Screencasts
> + Release Notes
>
> + Hub branding/doc
> + Terms of Service, Privacy Policy
> + NOC Run Book
>
> + Vision document
> + OSAF FAQ
> + OSAF website (push out)
> + Sundry blog/wiki/website details
>
> + Announcements, blending into launch plan
>
> *Jared*: I think I need a more clear picture of Hub branding/doc tasks,
> beyond updating the FAQ. I know we've talked about them, but a pointer
> to a clear summary would help me.
>
> *All*: Any missing big ticket items? Perhaps the thing to do is set
> dates for completed draft and final copy.
>
> Launch Plan Countdown: I'll integrate Ted's proposal, and follow up with
> any questions after I've done that.
>
> Cheers,
> Katie
>
>
> _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
>
> Open Source Applications Foundation "General" mailing list
> http://lists.osafoundation.org/mailman/listinfo/general
More information about the General
mailing list