Highlights

     * Chandler M5 due Sept 7. Down to 332 bugs in 0.6. Merged 
Set/Collection branch into trunk successfully.

Application

     * Progress: Branch merge done
     * Plans: m5 bugs (regressions caused by Set/Collection work)

Services, Dev Platform

     * Progress: I18n plan evolution and implementation. Certificate 
handling, sharing, timezone and Set fixes. Doc generation work. 
Performance improvements.
     * Plans: Twisted reactor changes and code review. Bug fixing. More 
performance work. Finish recurrences.

QA, Build

     * Progress: Tested Set branch and checkpoint build after merge. 
Added performance and acceptance test cases to CATS. Bonsai/SVN 
integration proceeding. Converted Zanshin to FSFS. External makefile 
now non-recursive. Continuous builds for Cosmo.
     * Plans: Extend CATS for use by developers. More work on external 
makefile. Proposal for instrumentation in Chandler. Retriage build bugs 
to account for m6. Refactor epydoc generation (hardhat and cron jobs).

Cosmo, Scooby

     * Progress: Tomcat upgrade; milestone 0.2-4 (nearing completion and 
release of 0.2)
     * Plans: iCal interoperability, Scooby week view developments.

IT

     * Progress: Server for Cosmo demo installed at ISC, running, and 
basically available. First real SSL cert purchased and installed.
     * Plans: New Silk-dedicated host for QA. More SSL certs. Some work 
delayed while Chris is gone.
     * Personnel: Chris away Sept 2-19

Community

     * Plans: IRC next week: performance and profiling. CalConnect 
roundtable and interop testing hosted by OSAF Sept 13-15. Westwood 
Advisory Council meeting Sept 22 in Pittsburgh (Lisa, Sheila, Mitch).