Highlights

     * Chandler: To merge or not to merge, that is the question [for the 
branch]. We won’t try for the m5 milestone until the branch is merged 
and return to QA acceptability.

Design

     * Progress: Demo and status for CSG meeting.
     * Plans: Floss Usability Sprint (Mimi OOF M/T/W. Friday: 
presentation for California Digital Library. Extensibility discussions. 
A ton of 0.7 planning tasks.

Applications:

     * Progress : Progress on all m5 tasks. Branch is now only a couple 
of bugs away of being merged.
     * Plan : Merge branch in trunk. Finish all m5 tasks.
     * Problems : m5 delayed as long as we don’t have the branch and 
trunk merged. Performance went really down with recent addition. Need 
to nail why before 0.6 out.

Services and Dev Platform

     * Progress: Content model cleanup (in code). API cleanup work 
carried to sample parcels. Revision to i18n string translation model. 
Timezone bug fixes.
     * Plans: Continue working on set/collection branch integration. 
Continue content model cleanup to wiki. More resources on performance. 
Timezone bug fixes.

QA/Build

     * Progress: CATS rearchitecture. New perf test cases. Tested 
recurrence and timezone feature work. ICU/PyICU upgraded. Zanshin 
revved.
     * Plans: Branch acceptability testing. Simplify CATS setup script. 
Upgrade libxml2.

Cosmo/Scooby

     * Progress: Facelift to Cosmo GUI
     * Plans: Apple iCal interoperability

IT

     * Progress: Cosmo demo server hardware built and awaiting install 
at colo this week. IT app dev server now in use.
     * Plans: Real SSL certs. Server backups improved. Some work delayed 
while Chris is gone.
     * Personnel: Chris Haumesser on vacation Sept 2-20

Community

     * Progress: CSG/WAC recalibration meeting past and tentatively 
successful — communication definitely happened
     * Plans: Debrief from the recalibration meeting. More planning for 
CalConnect meeting Sept 13-15. Start preparing for next CSG meeting 
Sept 21-23. IRC topic this week: i18n.