[Cosmo-dev] Cosmo 0.9 date

Matthew Eernisse mde at osafoundation.org
Wed Oct 17 13:32:00 PDT 2007


To get calendar overlay in for 0.9 would mean merging the overlay branch 
to trunk by sometime Friday.

It's definitely ready for some testing -- but does QA want to start 
testing before Friday with a local build of the overlay branch?

What do y'all think?


Matthew

Ted Leung wrote:
> I'd like to propose that we freeze 0.9 this Friday and start testing on 
> Monday 10/22, with an eye to a release at the end of that week.
> 
> TEd
> 
> On Oct 10, 2007, at 3:00 PM, Ted Leung wrote:
> 
>> Ok,
>>
>> Since we are looking at this, I'd propose that we do a 2 week 0.9 - 
>> particularly to get calendar overlays out to the world.   We can 
>> revisit the duration for subsequent releases after we size up the 
>> split work.
>>
>> Ted
>>
>> On Oct 9, 2007, at 5:51 PM, Brian Moseley wrote:
>>
>>> On 10/9/07, Ted Leung <twl at osafoundation.org> wrote:
>>>> Do we have any idea of the size of such an effort?
>>>
>>> probably just a few days, but it depends on bear doing the dojo build
>>> work we talked about in last week's meeting.
>>> _______________________________________________
>>> cosmo-dev mailing list
>>> cosmo-dev at lists.osafoundation.org
>>> http://lists.osafoundation.org/mailman/listinfo/cosmo-dev
>>
>> _______________________________________________
>> cosmo-dev mailing list
>> cosmo-dev at lists.osafoundation.org
>> http://lists.osafoundation.org/mailman/listinfo/cosmo-dev
> 
> _______________________________________________
> cosmo-dev mailing list
> cosmo-dev at lists.osafoundation.org
> http://lists.osafoundation.org/mailman/listinfo/cosmo-dev
> 



More information about the cosmo-dev mailing list