Doh, should have said "beginning of January deadline". I sure hope we 
can hit a January deadline!

Cheers,
Katie

Katie Capps Parlante wrote:
> Morgen and I were discussing the steps for the sharing format 
> implementation in more detail, in particular how they might fit up with 
> the schedule and dependencies. I thought I'd write this up on the Cosmo 
> list to make sure we're all in sync.
> 
> He listed out these tasks:
> A. EIM record definitions         (first pass done)
> B. XML serialization              (discussions in progress)
> C. Implement importer/exporter callbacks
>    - records --> items, items --> records
>    - xml --> records, records --> xml
> D. Implement synchronization/conflict detection algorithm
> E. Dump/reload items to files
> F. Hook up to DAV                 (current plan is to skip this step)
> G. Hook up to morse-code
> 
> A couple of notes:
> - We have not finalized the domain model on the Chandler side, so we 
> could still need make changes to the EIM record definitions. In 
> particular we'll need to review them for changes made to the recurrence 
> implementation, for dashboard/triage support, for changes made to the 
> mail schema, and for edit/update workflow support. (Edit/update workflow 
> is about knowing who made the last edit, change notifications, etc.)
> 
> - Morgen is working on (C: importer/exporter callbacks) now, and expects 
> that to take him ~3 weeks. He'll do a first pass at (E: dump/reload) as 
> a way of testing the importer/exporter callbacks.
> 
> - The EIM API (and implementation) to support (C: importer/exporter 
> callbacks) is ready. The EIM API (and implementation) to support (D: 
> sync implementation) is happening in parallel with (C: importer/exporter 
> callbacks).
> 
> - After previous discussions with BCM and Randy, we expect to skip (F: 
> hook up to DAV) altogether and go straight to morse-code. The one worry 
> we have is that we won't be able to hit a January deadline. An 
> alternative is to have EIM-over-DAV up and running as a first stage, in 
> January, as this will be quicker to get up and running. Another 
> alternative is to get Andi to help with the protocol work to bring in 
> the schedule.
> 
> Does this fit everyone's expectations? Will making changes to EIM 
> records later in the process have a negative impact on Cosmo scheduling? 
> Any other thoughts/concerns?
> 
> Cheers,
> Katie
> _______________________________________________