[Cosmo-dev] Sharing work plan
Katie Capps Parlante
capps at osafoundation.org
Fri Dec 1 14:53:10 PST 2006
Doh, should have said "beginning of January deadline". I sure hope we
can hit a January deadline!
Cheers,
Katie
Katie Capps Parlante wrote:
> Morgen and I were discussing the steps for the sharing format
> implementation in more detail, in particular how they might fit up with
> the schedule and dependencies. I thought I'd write this up on the Cosmo
> list to make sure we're all in sync.
>
> He listed out these tasks:
> A. EIM record definitions (first pass done)
> B. XML serialization (discussions in progress)
> C. Implement importer/exporter callbacks
> - records --> items, items --> records
> - xml --> records, records --> xml
> D. Implement synchronization/conflict detection algorithm
> E. Dump/reload items to files
> F. Hook up to DAV (current plan is to skip this step)
> G. Hook up to morse-code
>
> A couple of notes:
> - We have not finalized the domain model on the Chandler side, so we
> could still need make changes to the EIM record definitions. In
> particular we'll need to review them for changes made to the recurrence
> implementation, for dashboard/triage support, for changes made to the
> mail schema, and for edit/update workflow support. (Edit/update workflow
> is about knowing who made the last edit, change notifications, etc.)
>
> - Morgen is working on (C: importer/exporter callbacks) now, and expects
> that to take him ~3 weeks. He'll do a first pass at (E: dump/reload) as
> a way of testing the importer/exporter callbacks.
>
> - The EIM API (and implementation) to support (C: importer/exporter
> callbacks) is ready. The EIM API (and implementation) to support (D:
> sync implementation) is happening in parallel with (C: importer/exporter
> callbacks).
>
> - After previous discussions with BCM and Randy, we expect to skip (F:
> hook up to DAV) altogether and go straight to morse-code. The one worry
> we have is that we won't be able to hit a January deadline. An
> alternative is to have EIM-over-DAV up and running as a first stage, in
> January, as this will be quicker to get up and running. Another
> alternative is to get Andi to help with the protocol work to bring in
> the schedule.
>
> Does this fit everyone's expectations? Will making changes to EIM
> records later in the process have a negative impact on Cosmo scheduling?
> Any other thoughts/concerns?
>
> Cheers,
> Katie
> _______________________________________________
> cosmo-dev mailing list
> cosmo-dev at lists.osafoundation.org
> http://lists.osafoundation.org/mailman/listinfo/cosmo-dev
More information about the cosmo-dev
mailing list