[Chandler-dev] New Chandler Preview schedule

Philippe Bossut pbossut at osafoundation.org
Wed Mar 7 17:20:14 PST 2007


Hi,

We've been reviewing the Preview schedule in the last week. While it was 
clear that we needed to slip the FC milestone so that all required 
features could make it, we wanted to review the entire schedule so that 
the various parts (desktop, server and web UI) could readjust their own 
schedule and feature set.

We now agreed on such a schedule. Not only did we changed some dates and 
durations but we also added details to what happens during the various 
inter milestones periods as well as added one milestone.

So, for Chandler desktop, here are the main changes:
- added 3 weeks to the FC (3/26)
- added a 3 weeks "Performance tuning" period dedicated to performance 
improvement
- increased the debug period to 8 full weeks
- added precision to the milestones exit criteria so that we can qualify 
if a milestone is reached or not (see 
http://wiki.osafoundation.org/Projects/MilestonesDefinitionAndExitCriteria)

Putting things in few lines, here's how the schedule looks like right 
now (more details 
http://wiki.osafoundation.org/Projects/ChandlerMilestoneSchedule):
- Feature Freeze: 03/26 : all "tasks" in ready to be tested
    -> 3 weeks of perf work
- Performance Milestone (new):  04/16 : perf work done for most devs 
(some might still work on this during the debug period depending on what 
we discover during the 3 weeks perf tuning period)
    -> 8 weeks of bug fixing
- Code Complete: 06/11
    -> 2 weeks of critical bugs and blockers test/fix
- Release Candidate: 06/25
    -> 1 week of RC test and pre launch activities
- Launch: 06/29

We feel that this schedule is more realistic and will allow us to reach 
the feature and quality bar we want for this Preview. Sheila will be 
talking in more details about the entire Preview Countdown schedule and 
activities during tomorrow's staff meeting.

Cheers,
- Philippe