Hi,

Here's the notes of our 1pm meeting on Chandler Feature Complete 
milestone status:

Outstanding bugs:
-----------------------
 * 6553 (capps): Committed code this morning, will mark fix as soon as 
the TBox cycles green
 * 7766 (rae and robin): Checked a fix in the wx repo, waiting for Reid 
to call the new code in Chandler and test then we'll make a tarball. We 
decided during the meeting not to wait for the Chandler code change to 
roll a new wx tarball so that we can test Reid's fix as soon as it 
becomes available. This whole process will take 1/2 day so it's delaying 
FC till Monday morning.
 * 8145 (heikki): Proposed solution didn't work, is trying another 
approach to solve the issue. This needs to be fixed or encrypted 
passwords and Dump & Reload will be incompatible features. Heikki to try 
a couple of other ideas between now and Monday morning.

Decision on the FC Status:
----------------------------------
 * We're down to 2 tasks (7766 and 8145)
 * Since both seem to be on the verge of getting fixed, we decided to 
wait till Monday morning before declaring FC reached
 * In the meantime, no one is blocked (we're not branching and we're not 
changing radically the processes) and is free to switch to the 
Performance Tweaking phase

Cheers,
- Philippe